Scope Of Work Refurbishment of Pool Filter

Project Detail

Pioneer Maintenance Services were commissioned by City & County of Swansea to refurbish their giant pool filters at one of their school sites. The job entailed digging out tons of spent media, cleaning inside of filter shell, remove and set aside base laterals and blank holes and then carry out shot blasting of all internal mild steel surfaces.

Once metal surfaces had been prepared after shot blasting was completed, we heat dried the shell to drive out any moisture and then apply three coats of twin pack epoxy. Finally, after the internal protective coatings had been applied, we cleaned and refitted base laterals, then recharge filters with graded support media and top filtering sand (0.5mm – 1.00mm).